PRINCE2 Practitioner certification is suitable for anyone managing projects. This could be as part of a formal project management function or a role which involves project management as part of day-to-day work. The Practitioner certification aims to confirm that you have sufficient knowledge and understanding to apply and tailor the method in a range of different project environments and scenarios.
Attaining your Practitioner qualification is only one part of becoming a successful and effective project manager. It is important to ensure that yous upplement this with real-life experience working on projects, in addition to investing in personal professional development and wider training.
The Practitioner is the second of the two PRINCE2 examinations you are required to pass to become a Registered PRINCE2 Practitioner.
This PRINCE2 examination is aiming to measure whether a candidate would be able to apply PRINCE2 to the running and managing of a project within an environment supporting PRINCE2. To this end they need to exhibit the competence required for the Foundation qualification, and show that they can apply and tune PRINCE2 to address the needs and problems of a specific project scenario, specifically, candidates must be able to:
Produce detailed explanations of all principles, themes and processes and worked examples of all PRINCE2 products as they might be applied to address the particular circumstances of a given project scenario
Show they understand the relationships between principles, themes and processes and PRINCE2 products and can apply this understanding
Demonstrate that they understand the reasons behind the principles, themes and processes of PRINCE2, and that they understand the principles underpinning these elements
Demonstrate their ability to tune PRINCE2 to different project circumstances.
Targetted Candidate
Project Managers
General Managers
Programme Managers
Team Managers and support staff
Staff who will have a defined role
Project Management Consultants.
Prerequisites
In order to sit the PRINCE2 Practitioner examination you must provide proof of having passed one of the following:
PRINCE2 Foundation
Project Management Professional (PMP)®
Certified Associate in Project Management (CAPM)®
IPMA Level A (Certified Projects Director)
IPMA Level B® (Certified Senior Project Manager)
IPMA Level C® (Certified Project Manager)
IPMA Level D® (Certified Project Management Associate)
Examination Format
150 minute exam duration
68 questions
38/68 required to pass = 55% pass mark
100% Money Back Pass Guarantee
PRINCE2-Practitioner PDF Sample Questions
PRINCE2-Practitioner Sample Questions
PRINCE2-Practitioner Dumps
PRINCE2-Practitioner Braindumps
PRINCE2-Practitioner Real Questions
PRINCE2-Practitioner Practice Test
PRINCE2-Practitioner dumps free
Prince2
PRINCE2-Practitioner
PRINCE2 Practitioner
http://killexams.com/pass4sure/exam-detail/PRINCE2-Practitioner
Question: 484
Introductory Info Extract from the Project Product Description (with errors) Question Which 2 statements apply to the Acceptance criteria section?
A. Amend entry 21 to 'Appearance - 12 photos each showing different members of staff.
B. Move entry 21 to Composition because the photos are part of the final product.
C. Delete entry 22 because the development of the new company logo is not within the scope of the Calendar project.
D. Move entry 23 to Derivation because the Data Protection Act already exists.
E. Delete entry 24 because this is NOT a suitable acceptance criteria for this project.
Answer: A,C.
Question: 485
Introductory Info Scenario - Additional Information - Product Description -
Quality notes from the Daily Log The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced
staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is
signed with the selected service provider. The service level agreement between MFH and the selected service provider will specify the type and quality of
service required. The selected service provider must follow the industry standards for providing outsourced services. MFH has a quality management
system which contains a document control procedure for all its documentation, however this does not include change management. All project documents
will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair. Extract from the draft
Quality Management Strategy (may contain errors) Introduction - 1. This document defines the approach to be taken to achieve the required quality levels
during the project. 2. The Project Board will have overall responsibility for the Quality Management Strategy. 3. Project Assurance will provide assurance
on the implementation of the Quality Management Strategy. Quality management procedure - Quality standards 4. The selected service provider will
operate to industry standards for providing outsourced services. 5. MFH document standards will be used. Records - 6. A Quality Register will be
maintained to record the planned quality events and the actual results from the quality activities. 7. Configuration Item Records will be maintained for
each product to describe its status, version and variant. 8. Approval records for products that require them will be stored in the quality database. Roles and
responsibilities - 9. The DIT will check that the employment contracts for outsourced staff adhere to employment law. 10. Team Managers will provide
details of quality checks that have been carried out. 11. Team Managers will ensure that the Quality Register is updated with the names of team members
who are involved in the review process. 12. The Senior User will review the Product Descriptions of the products to be produced by the selected service
provider to ensure that they can be achieved. Question Which is a correctly defined acceptance criterion for the service level agreement (SLA) with the
selected service provider?
A. B. Any changes to the SLmust be managed through formal change control.
B. Any changes to the SLA must be managed through formal change control.
C. External consultants are to assist in the creation of the SLA.
D. The selected service provider should be located locally.
Answer: A
Question: 486
Introductory Info Scenario - Additional Information - Product Description - Quality notes from the Daily Log The Director of Information Technology
Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected service provider. The service level agreement between
MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry
standards for providing outsourced services. MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management. All project documents will be subject to a quality review. Nominated products will
require a formal approval record signed-off by the quality review chair. Extract from the draft Quality Management Strategy (may contain errors)
Introduction - 1. This document defines the approach to be taken to achieve the required quality levels during the project. 2. The Project Board will have
overall responsibility for the Quality Management Strategy. 3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy. Quality management procedure - Quality standards 4. The selected service provider will operate to industry standards for providing outsourced
services. 5. MFH document standards will be used. Records - 6. A Quality Register will be maintained to record the planned quality events and the actual
results from the quality activities. 7. Configuration Item Records will be maintained for each product to describe its status, version and variant. 8.
Approval records for products that require them will be stored in the quality database. Roles and responsibilities - 9. The DIT will check that the
employment contracts for outsourced staff adhere to employment law. 10. Team Managers will provide details of quality checks that have been carried
out. 11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process. 12. The
Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
Question Which is a correctly defined acceptance criterion for the transferred facilities computer system?
A. Must be subject to regular back-ups.
B. Planned periods of shutdowns of the computer system must be kept to a minimum.
C. No (zero) loss of system functionality.
D. Back-up of data must be kept until the data is no longer needed.
Answer: C
Question: 487
Introductory Info Scenario - Additional Information - Product Description - Quality notes from the Daily Log The Director of Information Technology
Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected service provider. The service level agreement between
MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry
standards for providing outsourced services. MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management. All project documents will be subject to a quality review. Nominated products will
require a formal approval record signed-off by the quality review chair. Extract from the draft Quality Management Strategy (may contain errors)
Introduction - 1. This document defines the approach to be taken to achieve the required quality levels during the project. 2. The Project Board will have
overall responsibility for the Quality Management Strategy. 3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy. Quality management procedure - Quality standards 4. The selected service provider will operate to industry standards for providing outsourced
services. 5. MFH document standards will be used. Records - 6. A Quality Register will be maintained to record the planned quality events and the actual
results from the quality activities. 7. Configuration Item Records will be maintained for each product to describe its status, version and variant. 8.
Approval records for products that require them will be stored in the quality database. Roles and responsibilities - 9. The DIT will check that the
employment contracts for outsourced staff adhere to employment law. 10. Team Managers will provide details of quality checks that have been carried
out. 11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process. 12. The
Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
Question Which is a correctly defined acceptance criterion for the transferred staff?
A. No staff are to be left behind.
B. Staff should be transferred as soon as possible.
C. All legal requirements are adhered to for the transfer of staff.
D. Retained staff should be of reasonable competence to maintain the SLA.
Answer: C
Question: 488
Introductory Info Scenario - Additional Information - Product Description - Quality notes from the Daily Log The Director of Information Technology
Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected service provider. The service level agreement between
MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry
standards for providing outsourced services. MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management. All project documents will be subject to a quality review. Nominated products will
require a formal approval record signed-off by the quality review chair. Extract from the draft Quality Management Strategy (may contain errors)
Introduction - 1. This document defines the approach to be taken to achieve the required quality levels during the project. 2. The Project Board will have
overall responsibility for the Quality Management Strategy. 3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy. Quality management procedure - Quality standards 4. The selected service provider will operate to industry standards for providing outsourced
services. 5. MFH document standards will be used. Records - 6. A Quality Register will be maintained to record the planned quality events and the actual
results from the quality activities. 7. Configuration Item Records will be maintained for each product to describe its status, version and variant. 8.
Approval records for products that require them will be stored in the quality database. Roles and responsibilities - 9. The DIT will check that the
employment contracts for outsourced staff adhere to employment law. 10. Team Managers will provide details of quality checks that have been carried
out. 11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process. 12. The
Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
Question Which is a correctly defined acceptance criterion for the running cost of the outsourced service?
A. Must be kept to a minimum.
B. Must be kept to a level acceptable to the Ministry of Food Hygiene.
C. Subject to market conditions.
D. The annual increase to be less than half the rate of inflation.
Answer: D
Question: 489
Introductory Info Scenario - Additional Information - Product Description - Quality notes from the Daily Log The Director of Information Technology
Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected service provider. The service level agreement between
MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry
standards for providing outsourced services. MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management. All project documents will be subject to a quality review. Nominated products will
require a formal approval record signed-off by the quality review chair. Extract from the draft Quality Management Strategy (may contain errors)
Introduction - 1. This document defines the approach to be taken to achieve the required quality levels during the project. 2. The Project Board will have
overall responsibility for the Quality Management Strategy. 3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy. Quality management procedure - Quality standards 4. The selected service provider will operate to industry standards for providing outsourced
services. 5. MFH document standards will be used. Records - 6. A Quality Register will be maintained to record the planned quality events and the actual
results from the quality activities. 7. Configuration Item Records will be maintained for each product to describe its status, version and variant. 8.
Approval records for products that require them will be stored in the quality database. Roles and responsibilities - 9. The DIT will check that the
employment contracts for outsourced staff adhere to employment law. 10. Team Managers will provide details of quality checks that have been carried
out. 11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process. 12. The
Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
Question Although it is not specified in the current corporate branding standards, the MFH corporate logo should be shown on the front page of the
service level agreement.
A. Obtain agreement from the Director of Facilities Division to amend this within the remaining +2 days tolerance.
B. Raise an issue (off-specification).
C. Raise an issue (request for change).
D. Accept this error as a concession
Answer: C
Question: 490
Introductory Info Scenario - Additional Information - Product Description - Quality notes from the Daily Log The Director of Information Technology
Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected service provider. The service level agreement between
MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry
standards for providing outsourced services. MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management. All project documents will be subject to a quality review. Nominated products will
require a formal approval record signed-off by the quality review chair. Extract from the draft Quality Management Strategy (may contain errors)
Introduction - 1. This document defines the approach to be taken to achieve the required quality levels during the project. 2. The Project Board will have
overall responsibility for the Quality Management Strategy. 3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy. Quality management procedure - Quality standards 4. The selected service provider will operate to industry standards for providing outsourced
services. 5. MFH document standards will be used. Records - 6. A Quality Register will be maintained to record the planned quality events and the actual
results from the quality activities. 7. Configuration Item Records will be maintained for each product to describe its status, version and variant. 8.
Approval records for products that require them will be stored in the quality database. Roles and responsibilities - 9. The DIT will check that the
employment contracts for outsourced staff adhere to employment law. 10. Team Managers will provide details of quality checks that have been carried
out. 11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process. 12. The
Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
Question The service level agreement looks like any other MFH document.
A. Obtain agreement from the Director of Facilities Division to redesign the service level agreement within the remaining +2 days tolerance.
B. Raise an issue (off-specification).
C. Accept this error as a concession.
D. No action required.
Answer: D
Question: 491
Introductory Info Scenario - Additional Information - Product Description - Quality notes from the Daily Log The Director of Information Technology
Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected service provider. The service level agreement between
MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry
standards for providing outsourced services. MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management. All project documents will be subject to a quality review. Nominated products will
require a formal approval record signed-off by the quality review chair. Extract from the draft Quality Management Strategy (may contain errors)
Introduction - 1. This document defines the approach to be taken to achieve the required quality levels during the project. 2. The Project Board will have
overall responsibility for the Quality Management Strategy. 3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy. Quality management procedure - Quality standards 4. The selected service provider will operate to industry standards for providing outsourced
services. 5. MFH document standards will be used. Records - 6. A Quality Register will be maintained to record the planned quality events and the actual
results from the quality activities. 7. Configuration Item Records will be maintained for each product to describe its status, version and variant. 8.
Approval records for products that require them will be stored in the quality database. Roles and responsibilities - 9. The DIT will check that the
employment contracts for outsourced staff adhere to employment law. 10. Team Managers will provide details of quality checks that have been carried
out. 11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process. 12. The
Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
Question None of the reviewers have proof-reading skills.
A. Record an action to request that Project Assurance identify a proof-reader who can, within the next 2 days, complete the check for typographical errors.
B. Ask the reviewers present at the meeting to conduct a proof-reading exercise and pass any comments to the author within 2 days.
C. Contact Project Assurance to find appropriate resources to come into the review.
D. No action required.
Answer: A
Question: 492
Introductory Info Scenario - Additional Information - Product Description - Quality notes from the Daily Log The Director of Information Technology
Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected service provider. The service level agreement between
MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry
standards for providing outsourced services. MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management. All project documents will be subject to a quality review. Nominated products will
require a formal approval record signed-off by the quality review chair. Extract from the draft Quality Management Strategy (may contain errors)
Introduction - 1. This document defines the approach to be taken to achieve the required quality levels during the project. 2. The Project Board will have
overall responsibility for the Quality Management Strategy. 3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy. Quality management procedure - Quality standards 4. The selected service provider will operate to industry standards for providing outsourced
services. 5. MFH document standards will be used. Records - 6. A Quality Register will be maintained to record the planned quality events and the actual
results from the quality activities. 7. Configuration Item Records will be maintained for each product to describe its status, version and variant. 8.
Approval records for products that require them will be stored in the quality database. Roles and responsibilities - 9. The DIT will check that the
employment contracts for outsourced staff adhere to employment law. 10. Team Managers will provide details of quality checks that have been carried
out. 11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process. 12. The
Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
Question The service level agreement contains a number of technical terms that are missing from its glossary of terms.
A. Obtain agreement from the Director of Facilities Division to add these into the glossary of terms within the remaining +2 days tolerance.
B. Raise an issue (off-specification).
C. Raise an issue (request for change).
D. No action required.
Answer: A
Question: 493
Introductory Info Scenario - Additional Information - Product Description - Quality notes from the Daily Log The Director of Information Technology
Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected service provider. The service level agreement between
MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry
standards for providing outsourced services. MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management. All project documents will be subject to a quality review. Nominated products will
require a formal approval record signed-off by the quality review chair. Extract from the draft Quality Management Strategy (may contain errors)
Introduction - 1. This document defines the approach to be taken to achieve the required quality levels during the project. 2. The Project Board will have
overall responsibility for the Quality Management Strategy. 3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy. Quality management procedure - Quality standards 4. The selected service provider will operate to industry standards for providing outsourced
services. 5. MFH document standards will be used. Records - 6. A Quality Register will be maintained to record the planned quality events and the actual
results from the quality activities. 7. Configuration Item Records will be maintained for each product to describe its status, version and variant. 8.
Approval records for products that require them will be stored in the quality database. Roles and responsibilities - 9. The DIT will check that the
employment contracts for outsourced staff adhere to employment law. 10. Team Managers will provide details of quality checks that have been carried
out. 11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process. 12. The
Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
Question Which statement applies to the Introduction section?
A. Delete entry 1 because the project approach is defined in the Project Brief.
B. Delete entry 2 because this is the Project Manager's responsibility.
C. Delete entry 3 because it is the Project Manager's responsibility to implement the Quality Management Strategy.
D. Move entry 3 to the Roles and responsibilities section because this is a quality responsibility.
Answer: D
Question: 494
Introductory Info Scenario - Additional Information - Product Description - Quality notes from the Daily Log The Director of Information Technology
Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected service provider. The service level agreement between
MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry
standards for providing outsourced services. MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management. All project documents will be subject to a quality review. Nominated products will
require a formal approval record signed-off by the quality review chair. Extract from the draft Quality Management Strategy (may contain errors)
Introduction - 1. This document defines the approach to be taken to achieve the required quality levels during the project. 2. The Project Board will have
overall responsibility for the Quality Management Strategy. 3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy. Quality management procedure - Quality standards 4. The selected service provider will operate to industry standards for providing outsourced
services. 5. MFH document standards will be used. Records - 6. A Quality Register will be maintained to record the planned quality events and the actual
results from the quality activities. 7. Configuration Item Records will be maintained for each product to describe its status, version and variant. 8.
Approval records for products that require them will be stored in the quality database. Roles and responsibilities - 9. The DIT will check that the
employment contracts for outsourced staff adhere to employment law. 10. Team Managers will provide details of quality checks that have been carried
out. 11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process. 12. The
Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
Question Which statement applies to the Quality standards section?
A. Delete entry 4 because external suppliers are responsible for applying any relevant standards to their work.
B. Delete entry 5 because the lack of a change management procedure makes the MFH document standards unsuitable.
C. Add 'All contracts must conform to current employment laws".
D. Add 'PRINCE2 change control procedures will be used to manage any changes to baselined products'.
Answer: C
Question: 495
Introductory Info Scenario - Additional Information - Product Description - Quality notes from the Daily Log The Director of Information Technology
Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected service provider. The service level agreement between
MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry
standards for providing outsourced services. MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management. All project documents will be subject to a quality review. Nominated products will
require a formal approval record signed-off by the quality review chair. Extract from the draft Quality Management Strategy (may contain errors)
Introduction - 1. This document defines the approach to be taken to achieve the required quality levels during the project. 2. The Project Board will have
overall responsibility for the Quality Management Strategy. 3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy. Quality management procedure - Quality standards 4. The selected service provider will operate to industry standards for providing outsourced
services. 5. MFH document standards will be used. Records - 6. A Quality Register will be maintained to record the planned quality events and the actual
results from the quality activities. 7. Configuration Item Records will be maintained for each product to describe its status, version and variant. 8.
Approval records for products that require them will be stored in the quality database. Roles and responsibilities - 9. The DIT will check that the
employment contracts for outsourced staff adhere to employment law. 10. Team Managers will provide details of quality checks that have been carried
out. 11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process. 12. The
Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
Question Which statement applies to the Records section?
A. Delete entry 6 because this information should be included in Stage or Team Plans.
B. Move entry 6 to the Reporting section because the information should be used to report on quality activities.
C. Delete entry 7 because this should be included in the Configuration Management Strategy.
D. Delete entry 8 because the results of quality reviews are recorded in the Quality Register.
Answer: C
Question: 496
Introductory Info Scenario - Additional Information - Product Description - Quality notes from the Daily Log The Director of Information Technology
Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected service provider. The service level agreement between
MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry
standards for providing outsourced services. MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management. All project documents will be subject to a quality review. Nominated products will
require a formal approval record signed-off by the quality review chair. Extract from the draft Quality Management Strategy (may contain errors)
Introduction - 1. This document defines the approach to be taken to achieve the required quality levels during the project. 2. The Project Board will have
overall responsibility for the Quality Management Strategy. 3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy. Quality management procedure - Quality standards 4. The selected service provider will operate to industry standards for providing outsourced
services. 5. MFH document standards will be used. Records - 6. A Quality Register will be maintained to record the planned quality events and the actual
results from the quality activities. 7. Configuration Item Records will be maintained for each product to describe its status, version and variant. 8.
Approval records for products that require them will be stored in the quality database. Roles and responsibilities - 9. The DIT will check that the
employment contracts for outsourced staff adhere to employment law. 10. Team Managers will provide details of quality checks that have been carried
out. 11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process. 12. The
Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
Question Which statement applies to the Roles and responsibilities section?
A. Delete entry 9 because this should only be recorded in the Product Description.
B. Delete entry 10 because this is the responsibility of the quality review chair.
C. Delete entry 11 because only the Project Manager can update the Quality Register.
D. Amend entry 12 because this is the responsibility of supplier assurance.
Answer: D
Question: 497
Introductory Info Product Summary - A list of customers will be collated. This will use existing information from the Accounts department about current
customers, and existing information from the Marketing department about prospective customers. Using the tariff of mailing costs available from the Post
Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they
decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details
of the competition to the staff. The chosen label design will then be selected from the competition entries. The photos for the calendar must be based on
existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be
created to show the required layout of each page. Product Breakdown Structure (contains errors)
Extract from Stage Plan for stage 3. (All entries are true statements but may not be shown under the correct heading or in the correct document).
For More exams visit https://killexams.com/vendors-exam-list
Kill your exam at First Attempt....Guaranteed!
Killexams VCE Exam Simulator 3.0.9
Killexams has introduced Online Test Engine (OTE) that supports iPhone, iPad, Android, Windows and Mac. PRINCE2-Practitioner Online Testing system will helps you to study and practice using any device. Our OTE provide all features to help you memorize and practice test questions and answers while you are travelling or visiting somewhere. It is best to Practice PRINCE2-Practitioner Exam Questions so that you can answer all the questions asked in test center. Our Test Engine uses Questions and Answers from Actual PRINCE2 Practitioner (6th Edition) exam.
Online Test Engine maintains performance records, performance graphs, explanations and references (if provided). Automated test preparation makes much easy to cover complete pool of questions in fastest way possible. PRINCE2-Practitioner Test Engine is updated on daily basis.
Valid as of today PRINCE2-Practitioner Exam dumps questions
At killexams.com, we provide the most recent and updated Exam Questions with actual PRINCE2-Practitioner examination questions and solutions for new subjects. Our PRINCE2-Practitioner braindumps and Free Exam PDF practice material will help you improve your understanding and achieve excellent results in your PRINCE2-Practitioner exam. We guarantee your success at the Test Center, covering all the purposes of the test and improving your familiarity with the PRINCE2-Practitioner exam. Pass without any doubt with our accurate questions.
Latest 2023 Updated PRINCE2-Practitioner Real Exam Questions
Passing the Prince2 PRINCE2-Practitioner exam requires more than just a superficial understanding of the course material and syllabus. Simply reading the PRINCE2-Practitioner course book is not enough. To ensure success, you need to familiarize yourself with the challenging questions that are asked in the actual PRINCE2-Practitioner exam. To achieve this, visit killexams.com and download their free PRINCE2-Practitioner braindumps sample questions to read. If you feel confident that you can memorize these PRINCE2-Practitioner questions, then you can register to download the complete set of Practice Test for PRINCE2-Practitioner braindumps. This will be your best move towards success. Install the VCE exam simulator on your computer, read and memorize PRINCE2-Practitioner braindumps, and take practice tests regularly with the VCE exam simulator. Once you feel fully prepared for the actual PRINCE2-Practitioner exam, visit the test center and register for the real exam. There is no shortcut to success when it comes to passing the Prince2 PRINCE2-Practitioner exam. You need to put in the time and effort to study and prepare properly. However, with the help of killexams.com, you can make the process much easier and increase your chances of success. By downloading the free PRINCE2-Practitioner braindumps sample questions, you can get an idea of the type of questions that will be asked in the actual PRINCE2-Practitioner exam. From there, you can register to download the complete set of Practice Test for PRINCE2-Practitioner braindumps and install the VCE exam simulator on your computer. With these resources at your disposal, you can read and memorize PRINCE2-Practitioner braindumps, take practice tests, and gauge your readiness for the actual PRINCE2-Practitioner exam. With persistence and hard work, you can clear your concepts and achieve success in the Prince2 PRINCE2-Practitioner exam.
Tags
PRINCE2-Practitioner dumps, PRINCE2-Practitioner braindumps, PRINCE2-Practitioner Questions and Answers, PRINCE2-Practitioner Practice Test, PRINCE2-Practitioner Actual Questions, Pass4sure PRINCE2-Practitioner, PRINCE2-Practitioner Practice Test, Download PRINCE2-Practitioner dumps, Free PRINCE2-Practitioner pdf, PRINCE2-Practitioner Question Bank, PRINCE2-Practitioner Real Questions, PRINCE2-Practitioner Cheat Sheet, PRINCE2-Practitioner Bootcamp, PRINCE2-Practitioner Download, PRINCE2-Practitioner VCE
Killexams Review | Reputation | Testimonials | Customer Feedback
killexams.com has had a very refreshing impact on my life because I used their material to pass my PRINCE2-Practitioner exam. Passing this exam is not easy, but I had access to the best reading dumps, and I am grateful for that.
Shahid nazir [2023-4-4]
After registering with killexams.com for exam help, I was able to rank high among my classmates, joining the ranks of the most outstanding students in my class. The unique and immensely beneficial resources provided by killexams.com, such as PRINCE2-Practitioner pdf, PRINCE2-Practitioner dumps, and PRINCE2-Practitioner books, proved to be invaluable in my preparation. I am grateful for the effective study tools provided by killexams.com, and recommend it to others.
Richard [2023-5-15]
During my preparation for the PRINCE2-Practitioner exam, I faced a tough time seeking help from friends as the material I received was mostly unclear and overwhelming. However, I stumbled upon killexams.com and its Questions and Answers material, which proved to be a valuable resource. With the help of their material, I was able to understand all the concepts and answer all the questions in the dump with precision, bringing endless happiness to my profession.
Shahid nazir [2023-4-8]
More PRINCE2-Practitioner testimonials...
PRINCE2-Practitioner PRINCE2 test
PRINCE2-Practitioner PRINCE2 test :: Article Creatorshallowness look at various
Do you consider in yourself? Do you give your self the credit score you deserve? shallowness is an essential component of personal happiness, satisfying relationships and fulfillment. This look at various is designed to consider your typical stage of vanity and assess no matter if you deserve to work in your self-graphic. Take this vanity look at various to discover your proper experience of self.
investigate here statements and point out how regularly or to what diploma you agree with them. to be able to receive the most accurate outcomes, please answer each and every question as truthfully as feasible.
After finishing this check you'll acquire a FREE picture record with a abstract assessment and graph. you are going to then have the choice to buy the entire results for $6.ninety five
This examine is intended for informational and amusement applications handiest. It isn't an alternative to skilled analysis or for the remedy of any fitness circumstance. if you want to are seeking for the suggestions of a licensed intellectual health practitioner that you may search Psychology trendy listing here.
References
PRINCE2 Practitioner (6th Edition) PDF Download
PRINCE2 Practitioner (6th Edition) PDF Braindumps
PRINCE2 Practitioner (6th Edition) Latest Topics
PRINCE2 Practitioner (6th Edition) PDF Braindumps
PRINCE2 Practitioner (6th Edition) PDF Braindumps
PRINCE2 Practitioner (6th Edition) Dumps
PRINCE2 Practitioner (6th Edition) PDF Questions
PRINCE2 Practitioner (6th Edition) braindumps
PRINCE2 Practitioner (6th Edition) PDF Questions
PRINCE2 Practitioner (6th Edition) PDF Dumps
PRINCE2 Practitioner (6th Edition) Cheatsheet
Frequently Asked Questions about Killexams Braindumps
I am facing issues in finding right dumps of PRINCE2-Practitioner exam?
This is very simple. Visit killexams.com. Register and download the latest and 100% valid PRINCE2-Practitioner dumps with VCE practice tests. You just need to memorize and practice these questions and reset ensured. You will pass the exam with good marks.
When It is good time to buy PRINCE2-Practitioner question bank?
You can register at killexams.com when you decide to prepare for your exam and have time to study and memorize the questions and answers. There are 3 months, 6 months, and 1-year download accounts available at killexams.com according to the actual test planning of candidates. It is always a good time to register and download the question bank because you will have enough time to study and memorize the exam dumps.
I had an old account, Can I use the same account for new exams?
Yes, you can use the same account for new exams. But if you buy exams and got a new account to download, you can still ask support to shift your exams to your old account.
Is Killexams.com Legit?
Of course, Killexams is fully legit as well as fully dependable. There are several functions that makes killexams.com genuine and legit. It provides up to par and 100 % valid exam dumps that contain real exams questions and answers. Price is surprisingly low as compared to many of the services on internet. The questions and answers are current on frequent basis together with most recent brain dumps. Killexams account make and product delivery is very fast. Report downloading is normally unlimited and very fast. Aid is available via Livechat and Contact. These are the features that makes killexams.com a robust website which provide exam dumps with real exams questions.
Other Sources
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) study tips
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) test prep
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) study help
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) PDF Download
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) exam format
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) tricks
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) Questions and Answers
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) Practice Questions
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) learn
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) PDF Braindumps
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) study tips
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) questions
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) Actual Questions
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) Study Guide
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) study tips
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) Cheatsheet
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) PDF Questions
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) real questions
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) Test Prep
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) techniques
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) exam syllabus
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) exam dumps
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) techniques
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) Exam Cram
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) PDF Download
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) syllabus
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) PDF Dumps
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) Actual Questions
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) syllabus
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) PDF Download
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) testing
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) information source
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) Latest Questions
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) PDF Dumps
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) Exam Questions
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) course outline
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) tricks
PRINCE2-Practitioner - PRINCE2 Practitioner (6th Edition) exam dumps
Which is the best dumps site of 2023?
There are several Questions and Answers provider in the market claiming that they provide Real Exam Questions, Braindumps, Practice Tests, Study Guides, cheat sheet and many other names, but most of them are re-sellers that do not update their contents frequently. Killexams.com is best website of Year 2023 that understands the issue candidates face when they spend their time studying obsolete contents taken from free pdf download sites or reseller sites. That is why killexams update Exam Questions and Answers with the same frequency as they are updated in Real Test. Exam Dumps provided by killexams.com are Reliable, Up-to-date and validated by Certified Professionals. They maintain Question Bank of valid Questions that is kept up-to-date by checking update on daily basis.
If you want to Pass your Exam Fast with improvement in your knowledge about latest course contents and topics, We recommend to Download PDF Exam Questions from killexams.com and get ready for actual exam. When you feel that you should register for Premium Version, Just choose visit killexams.com and register, you will receive your Username/Password in your Email within 5 to 10 minutes. All the future updates and changes in Questions and Answers will be provided in your Download Account. You can download Premium Exam Dumps files as many times as you want, There is no limit.
Killexams.com has provided VCE Practice Test Software to Practice your Exam by Taking Test Frequently. It asks the Real Exam Questions and Marks Your Progress. You can take test as many times as you want. There is no limit. It will make your test prep very fast and effective. When you start getting 100% Marks with complete Pool of Questions, you will be ready to take Actual Test. Go register for Test in Test Center and Enjoy your Success.
Important Braindumps Links
Below are some important links for test taking candidates
Medical Exams
Financial Exams
Language Exams
Entrance Tests
Healthcare Exams
Quality Assurance Exams
Project Management Exams
Teacher Qualification Exams
Banking Exams
Request an Exam
Search Any Exam